Question: Activities following a node have an earliest start time equal to the largest of the eariest finish times for all activities entering the node. can

Activities following a node
have an earliest start time equal to the largest of the eariest finish times for all activities entering the node.
can begin as soon as any activity preceding the node has been completed.
have a latest start time equal to the largest of the earliest finish times for all activities entering the node.
None of these are correct.
 Activities following a node have an earliest start time equal to