Question: Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 12, 18, and 10,

Activities G, P, and R are the immediate

Activities G, P, and R are the immediate

Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 12, 18, and 10, then the earliest start time for W is 10. O is 12. is 18. cannot be determined. An alpha (a) value of 0.4 will cause an exponential smoothing forecast to react more quickly to a sudden drop in demand than will an a equal to 0.2. O True False