Question: Activities in a project will need to be carefully managed to ensure the project comes to fruition by the time constraint and that all activities
Activities in a project will need to be carefully managed to ensure the project comes to fruition by the time constraint and that all activities will be sequenced correctly.
Review the Activity instruction provided below and draw the Network diagram for these activities:
The project starts with Activities A and B done concurrently. When A and B are finished, D can start. When A is finished, C can start. When D is finished, E can start. When C and E are finished, F can start. The project is complete when F is finished. include references