Question: Activities on the critical path Select one: O A. have no slack B. are the ones with the longest activity times C. have ES equal

Activities on the critical path Select one: O A.
Activities on the critical path Select one: O A. have no slack B. are the ones with the longest activity times C. have ES equal to EF D. have LS equal to LF