Question: Activities should _ _ _ _ the time intervals at which actual project progress will be reviewed and compared to planned progress. a . be
Activities should the time intervals at which actual project progress will be reviewed and compared to planned progress.
a
be any length of time, it doesn't matter the length
b
be longer in estimated duration than
c
not be longer in estimated duration than
d
be the same length in estimated duration as