Question: ACTIVITY 2 0 : STOPWATCH TIME STUDY CALCULATIONS 1 objectives: At the end of the activity the students are expected to: Page | - 1

ACTIVITY 20: STOPWATCH TIME STUDY CALCULATIONS 1
objectives: At the end of the activity the students are expected to:
Page |-107-
Acquire the skills on setting time standards using stopwatch time study formula.
Utilize cancellation of units to calculate time standards.
Gain the ability to use the time standard formula to solve other unknowns.
Apparatus: Calculators, solution sheets
Problems:
Compute for the standard output in pieces per hour (pc/hr) and standard time in hours per piece (hrspc) given the following: Assume: 8hrs? day as working shift.
a.300minpc
b.2.0secpc
c..450secpc
d.0.050minpc
What will be the labor cost per piece in #1, if labor rate is $350 per day?
How many machines should you buy and how many people should you hire if 3000 units are needed per shift and the machine standard time is 0.284 minutes per piece. How much will each unit cost if the operator is paid $10? hr. How many units (capacity) will be produced per shift? Assume: 1 shift production only.
 ACTIVITY 20: STOPWATCH TIME STUDY CALCULATIONS 1 objectives: At the end

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!