Question: Activity 2 : Gather and format the information ( obtain credit scores, organize customer - specific needs ) for analysis ( 5 minutes / loan

Activity 2: Gather and format the information (obtain credit scores, organize customer-specific needs) for analysis (5 minutes/loan).
Activity 3: Analyze the information: check the creditworthiness and decide the loan amount and APR to offer (7 minutes/loan).
Activity 4: Perform final checks on the loan offer (2 minutes/loan).
Activity 5: Call customer back with the new loan offer and close (4 minutes/loan).
The whole process is conducted by three workers in a worker-paced line. The assignment of tasks to workers is the following: Worker 1 does activity 1, Worker 2 does activities 2 and 3, and Worker 3 does activities 4 and 5. Each worker is paid $20 per hour. You can assume that there exists unlimited demand and that loans are only entering the process at the rate of the bottleneck.
(a)(2pt What is the bottleneck in the process?
(b)(2 pt) What are the costs of direct labor?
(c)(3 pt) Across all three workers, what is the average labor utilization?
(d)(3 pts) How would you rebalance the process to maximize process capacity, assuming that the five activities have to be carried out in the given order?
 Activity 2: Gather and format the information (obtain credit scores, organize

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!