Question: Activity 5. WORK STUDY 1. Compute the Standard Time in processing Passport by a travel agent if she has a performance rating of 115% with
Activity 5. WORK STUDY
1. Compute the Standard Time in processing Passport by a travel agent if she has a performance rating of 115% with time allowance of 20%.
NOTE: THE PROCESSING TIME PER CYCLE ARE IN DAYS.
Cycle Processing Time per Cycle (in days)
1 18
2 16
3 15
4 14
5 16
6 16
7 14
8 14
9 15
10 18
11 19
12 14
2. Compute the standard time in preparing milktea in a store where the crew rated with 97% efficiency and an allowance rating of 10%.
Orders Preparation Time per Cycle (in minutes)
1 10
2 8
3 11
4 12
5 11
6 10
7 8
8 9
9 10
10 10
11 11
12 13
13 14
14 12
15 9
16 8
17 12
18 13
19 12
20 10
3. A time study analyst timed an assembly operation for 30 cycles, and then computed the average
time per cycle, which was 18.75 minutes. The analyst assigned a performance rating of .96, and
decided that an appropriate allowance was 15 percent. Assume the allowance factor is based on the
workday. Determine the following: the observed time (OT), the normal time (NT), and the standard
time (ST).