Question: Activity A ---> Activity B ---> Activity C A short project consists of 3 sequential activities. The initial direct (normal time) costs for the 3

Activity A ---> Activity B ---> Activity C A

Activity A ---> Activity B ---> Activity C A short project consists of 3 sequential activities. The initial direct (normal time) costs for the 3 activities totals $3000. The indrect costs run $100 per day for the project that initially spanned 12 days. Activity Crash Cost (Slope, $/day) Max Crash Time (days) 62 2. B 40 3 C 79 Activity B was crashed by one day. Determine the change (increase or decrease) in the total project cost. (Input a negative value to represent a cost decrease.)