Question: Activity A B C D E F G H Predecessor A A, B C, D E E F, G Cc = crash cost No =

Activity A B C D E F G H Predecessor A A, B C, D

Activity A B C D E F G H Predecessor A A, B C, D E E F, G Cc = crash cost No = normal cost N CT = crash time = normal time Crash time (weeks) CT 8 9 11 8 6 5 3 9 Crash cost ($) Cc 600- 435 200 550 420 250 400 1100 Calculate Critical path with normal duration Critical path with crashed duration Final project duration after crashing Total crash cost Total days reduced Normal time (weeks) NT 10 12 13 10 8 7 4 10 Normal Cost ($) Nc 300 300 100 150 250 100 300 800