Question: Activity A B C D E F G H T Immediate Predecessor B A E D Optimistic Time 2 1 6 2 6 1 C,

Activity A B C D E F G H T Immediate Predecessor B A E D Optimistic Time 2 1 6 2 6 1 C, D F, G, H 1.2 Construct an AON network for the activities of this project. 3 5 Most Likely Time 6 4 2 7 4 10 3 6 11 Pessimistic Time 8 6 3 8 6 9 5 14 17 (9)

construc an AON network for the activities