Question: Activity A B C D E F LL The client of a project has requested the project team to crash 8 hours of time.
Activity A B C D E F LL The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? G H Normal Duration (hours) 2 3 5 3 6 1 7 10 Normal Cost ($) 10 15 25 20 30 5 35 50 Crash Duration Crash (hours) 2 2 4 1 4 1 6 7 Cost (S) 0 23 30 24 45 0 50 62 Immediate Predecessors None A B C C C.E. F D.G
Step by Step Solution
3.38 Rating (157 Votes )
There are 3 Steps involved in it
To determine the crash cost for 8 hours of timesavings we need to analyze the crash duration and cra... View full answer