Question: activity A has 6 days of total float and 2 days of free float: If activity A is delayed 4 days, which statement is correct?
activity A has 6 days of total float and 2 days of free float: If activity A is delayed 4 days, which statement is correct?
The completion date of the project will not be impacted but the successors will be impacted.
The successors of Activity A will also be delayed by 4 days.
The project will finish 2 days late.
Nothing will be impacted.