Question: Activity A Immediate Predecessor(s)Time (weeks) 3 B 4 2 D A . 4 E 5 A, B A, B, C F 2 G D, E

Activity A Immediate Predecessor(s)Time (weeks) 3

Activity A Immediate Predecessor(s)Time (weeks) 3 B 4 2 D A . 4 E 5 A, B A, B, C F 2 G D, E 1 H E 6 I E, F 2 J 4 G, H, I HT K 3 L | 6 Using Table 7.6, suppose activity D can be shortened from four days to one day. Assume all other activity times remain the same. How much shorter will the total project earliest completion time become