Question: Activity A is worth $ 5 0 0 , is finished, and cost $ 5 0 0 to do . Activity B is worth $

Activity A is worth $500, is finished, and cost $500 to do.
Activity B is worth $1000, is 75% finished, and has cost $700 to do so far.
Activity C is worth $100, is 50% finished, and has cost $90 to do so far.
What is the total EV for the project?
Question 2Select one:
a.
$1300
b.
$1600
c.
-$1075
d.
$1075