Question: Activity a m b Immediate Predecessor(s) Activity a m b Immediate Predecessor(s) A 3 6 9 - H 4 4 8 E, F B 2
Activity a m b Immediate Predecessor(s) Activity a m b Immediate Predecessor(s) A 3 6 9 - H 4 4 8 E, F B 2 2 5 - I 1 5 10 G, H C 6 6 6 A J 3 4 7 I D 5 9 13 A K 8 8 12 I E 1 9 18 B, C L 1 5 6 J F 1 5 6 D M 1 2 4 K G 3 7 9 D N 5 7 10 L, M
a) The expected completion time of the project =
________
days (round your response to two decimal places).
Part 3
The activities that represent the project's critical path are
________
.
Part 4
b) If the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in
53
days or less =
________
(round your response to two decimal places).
Part 5
c) Using the standard normal table
LOADING...
, the number of days that would result in 99% probability of completion =
________
days (round your response to two decimal places).