Question: Activity ABCDEFG Normal Time ( weeks ) Crash Time ( weeks ) 2 1 1 3 Normal Cost Total Cost with Crashing Immediate Predecessor (

Activity
ABCDEFG
Normal Time (weeks)
Crash Time (weeks)
2
1
1
3
Normal Cost
Total Cost with Crashing
Immediate Predecessor(s)
3
$2,000
$2,800
$1,650
$1,000
$350
$350
|||ABC
217624
$1,500
$1,820
3
1
2
$850
$1,000
$4,250
$1,800
$5,250
$2,400
D, E
a) Based on the given information regarding the activities for the project, the project completion date
b) To reduce the duration of the project to 10 weeks at the least cost, the following is the order of what needs to be followed while crashing the activities:
14 weeks.
The first activity to crash is D by 2 weeks at a per week crashing cost of 80 dollars.
Next, one should crash activity D and activity E by 2 weeks for an additional total per week crashing cost of 130 dollars.
c) New requirements are to reduce the project to 7 weeks. Continuing to crash the activities from 10 weeks based on the above crashing already completed, the following is the order for crashing:
Next activity to crash in order is
by 2 weeks at a per week crashing cost of dollars.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!