Question: Activity Activity Description Immediate Predecessor Time Estimates ( days ) o - m - p a Excavation - 3 - 4 - 6 b Lay

Activity Activity Description Immediate Predecessor Time Estimates (days)
o- m- p
a Excavation -3-4-6
b Lay foundation a 2-3-5
c Frame and roof b 2-4-5
d Lay drain tiles b 1-2-4
e Sewer (floor) drains b 1-2-3
f Install insulation c 2-4-5
g Pour basement floor e 2-3-5
h Rough plumbing, pipes e 2-4-7
i Install windows f 1-3-4
j Rough electrical wiring f 1-2-4
k Install air conditioners c,g 3-5-8
l Exterior brickwork i 5-6-10
m Install plasterboard, mud, plaster j,h,k 6-8-12
n Roof shingles, flushing l 2-3-6
o Attach gutter, downspouts n 1-2-5
p Grading d,o 2-3-7
q Lay subflooring m 3-4-6
r Lay driveway, walks and landscape p 4-6-10
s Finish carpentry q 3-5-12
t Kitchen cabinetry, sink and appliances q 2-4-8
u Bathroom cabinetry, fixtures q 2-3-6
v Painting the walls t,u 4-6-10
w Finish wood floors, lay carpet v,s 2-5-8
x Final electrical and light fixtures v 1-3-4
END r,w,x

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!