Question: Activity - Based Costing, Unit Cost, Ending Work - in - Process Inventory Salazar Company is a job - order costing firm that uses activity

Activity-Based Costing, Unit Cost, Ending Work-in-Process Inventory
Salazar Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Salazar identified three overhead activities and related drivers. Budgeted information for the year is as follows:
Activity Cost Driver Amount of Driver
Setting up design $156,000 Setups 1,200
Purchasing 186,000 Number of parts 15,000
Other overhead 415,000 Direct labor hours 50,000
Salazar worked on five jobs in March. Data are as follows:
Job 15 Job 16 Job 17 Job 18 Job 19
Balance, March 1 $34,500 $39,890 $24,090 $0 $0
Direct materials $28,000 $37,900 $25,350 $11,000 $13,580
Direct labor $10,000 $8,500 $23,000 $12,700 $8,000
Setups 201435815
Number of parts 150180200500300
Direct labor hours 6505801,600870520
By March 31, Jobs 15,16, and 17 were completed and sold. The remaining jobs were in process.
Required:
Question Content Area
1. Calculate the activity rates for each of the three overhead activities. If required, round your answers to the nearest cent.
Setup rate $fill in the blank 04084bf44feff87_1 per set up
Purchasing rate $fill in the blank 04084bf44feff87_2 per part
Other overhead rate $fill in the blank 04084bf44feff87_3 per direct labor hour
Question Content Area
2. Prepare job-order cost sheets for each job showing all costs through March 31. What is the cost of each job by the end of March?. If an amount is zero, enter "0".
Salazar Company
Job-Order Cost Sheets
blank
Job 15 Job 16 Job 17 Job 18 Job 19
Balance, March 1 $fill in the blank fe08370b003df9b_1 $fill in the blank fe08370b003df9b_2 $fill in the blank fe08370b003df9b_3 $fill in the blank fe08370b003df9b_4 $fill in the blank fe08370b003df9b_5
Direct materials fill in the blank fe08370b003df9b_6 fill in the blank fe08370b003df9b_7 fill in the blank fe08370b003df9b_8 fill in the blank fe08370b003df9b_9 fill in the blank fe08370b003df9b_10
Direct labor fill in the blank fe08370b003df9b_11 fill in the blank fe08370b003df9b_12 fill in the blank fe08370b003df9b_13 fill in the blank fe08370b003df9b_14 fill in the blank fe08370b003df9b_15
Applied overhead:
Setups fill in the blank fe08370b003df9b_16 fill in the blank fe08370b003df9b_17 fill in the blank fe08370b003df9b_18 fill in the blank fe08370b003df9b_19 fill in the blank fe08370b003df9b_20
Purchasing fill in the blank fe08370b003df9b_21 fill in the blank fe08370b003df9b_22 fill in the blank fe08370b003df9b_23 fill in the blank fe08370b003df9b_24 fill in the blank fe08370b003df9b_25
Other overhead fill in the blank fe08370b003df9b_26 fill in the blank fe08370b003df9b_27 fill in the blank fe08370b003df9b_28 fill in the blank fe08370b003df9b_29 fill in the blank fe08370b003df9b_30
Total cost $fill in the blank fe08370b003df9b_31 $fill in the blank fe08370b003df9b_32 $fill in the blank fe08370b003df9b_33 $fill in the blank fe08370b003df9b_34 $fill in the blank fe08370b003df9b_35
Question Content Area
3. Calculate the balance in Work in Process on March 31.
$fill in the blank a2fbc9fc0045063_1
4. Calculate the cost of goods sold for March.
$fill in the blank a2fbc9fc0045063_2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!