Question: Activity - Based Life - Cycle Costing Unit - based system: Variable conversion activity rate: $ 1 1 0 per direct labor hour Material usage

Activity-Based Life-Cycle Costing
Unit-based system:
Variable conversion activity rate: $110 per direct labor hour
Material usage rate: $10 per part
ABC system:
Labor usage: $15 per direct labor hour
Material usage (direct materials): $20 per part
Machining: $75 per machine hour
Purchasing activity: $170 per purchase order
Setup activity: $3,500 per setup hour
Warranty activity: $600 per returned unit (usually requires extensive rework)
Customer repair cost: $25 per repair hour (average)
Activity and Resource Information (annual estimates)
Required:
Select the lower-cost design using unit-based costing.
:
Are logistical and post-purchase activities considered in this analysis?
Select the lower-cost design using ABC analysis.
.
What if the post-purchase cost was an environmental contaminant and amounted to $10 per unit for Design A and 40 per unit for Design B ? Compute the Post-purchase cost for each design.
Post-Purchase Cost
 Activity-Based Life-Cycle Costing Unit-based system: Variable conversion activity rate: $110 per

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!