Question: Activity C on a CPM network has predecessors A and B, and has successor D and E. C has duration 5. B's late finish is
- Activity C on a CPM network has predecessors A and B, and has successor D and E. C has duration 5. B's late finish is 18, while A's is 20. D's late start is 14, while Es is 16. Which of the following is definitely true?
- C is critical and has zero slack.
- C is not critical and has slack times.
- B is a critical activity.
- D is a critical activity.
- E is a critical activity.
- None of the above.