Question: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 195,000 10,000 MHs Machine setups Number of setups $ 67,500 150 setups
| Activity Cost Pool | Activity Measure | Estimated Overhead Cost | Expected Activity | ||
| Machining | Machine-hours | $ | 195,000 | 10,000 | MHs |
| Machine setups | Number of setups | $ | 67,500 | 150 | setups |
| Product design | Number of products | $ | 79,000 | 2 | products |
| General factory | Direct labor-hours | $ | 245,000 | 12,000 | DLHs |
| Activity Measure | Product Y | Product Z |
| Machine-hours | 6,500 | 3,500 |
| Number of setups | 50 | 100 |
| Number of products | 1 | 1 |
| Direct labor-hours | 7,500 | 4,500 |
|
| ||
13. Using the ABC system, what percentage of Machine Setups cost is assigned to Product Y and Product Z? (Round your "Percentage" answers to 2 decimal places.)
14. Using the ABC system, what percentage of the Product Design cost is assigned to Product Y and Product Z?
15. Using the ABC system, what percentage of the General Factory cost is assigned to Product Y and Product Z? (Round your "Percentage" answers to 2 decimal place.)