Question: activity cost pool activity measure total cost total activity machining machine-hours $579600 18000 MHs machine set ups number of set ups $420000 700 setups product
activity cost pool activity measure total cost total activity
machining machine-hours $579600 18000 MHs
machine set ups number of set ups $420000 700 setups
product design number of products $56000 2 products
order size direct labor hrs $290000 20000 DLHs
Avtivity measure Product B820 Product P99Y
machining 10000 8000
number ofset ups 450 250
number of products 1 1
Direct labor hrs 8400 11600
1.Calculate the plant wide predetermined manufacturing overhead rate:
2.using the plantwide overhead rate calculated above, hpw much manufacturing OH cost would be allocated to product B820?
3.using the ABC system calculate the rates for each activity cost pool
PLEASE and thanks.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts