Question: Activity Cost Pool Supporting direct labor Machine processing Machine setups Production orders Shipments Product sustaining Activity Rates $ 10 per direct labor-hour 2 per machine-hour
Activity Cost Pool Supporting direct labor Machine processing Machine setups Production orders Shipments Product sustaining Activity Rates $ 10 per direct labor-hour 2 per machine-hour $ 45 per setup $ 160 per order $ 115 per shipment $ 850 per product Activity data have been supplied for the following two products: Number of units produced per year Direct labor-hours Machine-hours Machine setups Production orders Shipments Product sustaining Total Expected Activity K425 M67 200 2,000 900 40 3,000 30 5 1 5 1 10 1 1 1 Required: How much total overhead cost would be assigned to K425 and M67 using the activity-based costing system? K425 M67 Activity Cost Pool Supporting direct labor Machine processing Machine setups Production orders Shipments