Question: Activity Crash cost time A B D E Predecessor Normal activity 2 8 4 B 1 B 2 CD 5 E 6 Crash time Normal

Activity Crash cost time A B D E Predecessor

Activity Crash cost time A B D E Predecessor Normal activity 2 8 4 B 1 B 2 CD 5 E 6 Crash time Normal cost 1 10000 5 15000 3 20000 1 7000 1 8000 3 10000 2 12000 15000 21000 24000 7000 15000 16000 36000 F G Find the minimum possible time of the project and the cost associated with this