Question: Activity data, Precedence relations and Resources data II . REQUIREMENTS 1 . Determine the critical activities and calculate the project duration 2 . Allocate resources

Activity data, Precedence relations and Resources data
II. REQUIREMENTS
1. Determine the critical activities and calculate the project duration
2. Allocate resources
3. Level resources
\table[[Activity,Immediate,Normal,Resources],[,Duration (weeks),R1(laborer),R2(carpenter)],[A,cdots+-,2,2,1],[B,A,4,4,2],[C,A,4,4,2],[D,A,3,3,1],[E,B,4,4,1],[F,C,7,4,4],[G,C,2,2,1],[H,D,5,4,3],[J,F,2,2,1],[K,H,5,4,3],[L,J,2,2,1],[M,E,G,L,3,3,2],[N,K,M,2,2,1]]
*A maximum value of 4 and 6 has been specified for resources types R1 and R2 respectively during the entire project.
 Activity data, Precedence relations and Resources data II. REQUIREMENTS 1. Determine

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!