Question: Activity Depends on Duration (week) optimistic probable pesimistic A 1 3 5 B A 3 4 5 C A 2 5 8 D 2 6

Activity Depends on Duration (week) optimistic

Activity Depends on Duration (week) optimistic probable pesimistic A 1 3 5 B A 3 4 5 C A 2 5 8 D 2 6 10 E B,C,D 2 3 4 F B,C,D 1 4 7 G B,C,D 3 5 7 H E,F,G 1 2 3 Deficiencies were found in one school. 18 weeks were given to detect these deficiencies. The staff has created the above table. Find the probability of finishing the project in 18 weeks. Use the PERT method. A- 88.3% chance to complete before 18 weeks B- 68% chance to complete before 18 weeks C- 72% chance to complete before 18 weeks D- 48.3% chance to complete before 18 weeks E- 98.5% chance to complete before 18 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!