Question: Activity Description Activity Time Preceding Activity 1 Problem Definition 3 None 2 System Analysis 4 1 3 Software Configuration 10 2 4 Hardware Development 5
Activity Description Activity Time Preceding Activity
1 Problem Definition 3 None
2 System Analysis 4 1
3 Software Configuration 10 2
4 Hardware Development 5 3
5 Software Analysis 9 3
6 Component Acceptance 7 3
7 Design Prototype 15 5, 6
8 Design Database 13 7
9 Develop Prototype 12 7
10 Develop Database 9 8, 9
11 Test Prototype 5 4
12 Test Database 7 11
13 Implement System 6 10, 12
What is early start for Activity 7? Complete forward and backward pass.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts