Question: ACTIVITY DESCRIPTION Duration(minutes) Start Time Finish Time Power down 0 8:00 8:00 Remove old fusebox 40 8:00 8:40 install new fusebox 80 8:40 10:00 cut
| ACTIVITY DESCRIPTION | Duration(minutes) | Start Time | Finish Time |
| Power down | 0 | 8:00 | 8:00 |
| Remove old fusebox | 40 | 8:00 | 8:40 |
| install new fusebox | 80 | 8:40 | 10:00 |
| cut cable channelling | 200 | 8:00 | 11:20 |
| fit new cable channelling | 140 | 10:00 | 12:20 |
| lay new cable | 120 | 12:20 | 14:20 |
| connect to fusebox | 40 | 14:20 | 15:00 |
| connect to machine | 20 | 14:20 | 14:40 |
| power up | 0 | 15:00 | 15:00 |
| test machine | 60 | 15:00 | 16:00 |
Based on the Table above complete a Gantt Chart?