Question: Activity Description Immediate Predecessor Estimated Completion Time (weeks) A Develop product design --- 6 B Plan market research --- 2 C Prepare routing A 3
| Activity | Description | Immediate Predecessor | Estimated Completion Time (weeks) |
| A | Develop product design | --- | 6 |
| B | Plan market research | --- | 2 |
| C | Prepare routing | A | 3 |
| D | Build prototype | A | 5 |
| E | Prepare marketing brochure | A, B | 3 |
| F | Prepare cost estimate | C | 2 |
| G | Do preliminary design testing | D | 3 |
| H | Complete Market survey | B, E | 4 |
| I | Prepare pricing and forecast report | H | 2 |
| J | Prepare final report | F, G, I | 2 |
| 1. Draw the PERT Diagram on a separate sheet of paper based on this Activity List. | |||||||||
| 2. Check the next sheet ("Project Flow") for a solution and compare your work! | |||||||||
| 3. Continue to the "Project Flow" sheet for further instructions. | |||||||||
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock