Question: Activity Description Immediate Predecessor Estimated Completion Time (weeks) A Develop product design --- 6 B Plan market research --- 2 C Prepare routing A 3

Activity Description Immediate Predecessor Estimated Completion Time (weeks)
A Develop product design --- 6
B Plan market research --- 2
C Prepare routing A 3
D Build prototype A 5
E Prepare marketing brochure A, B 3
F Prepare cost estimate C 2
G Do preliminary design testing D 3
H Complete Market survey B, E 4
I Prepare pricing and forecast report H 2
J Prepare final report F, G, I 2
1. Draw the PERT Diagram on a separate sheet of paper based on this Activity List.
2. Check the next sheet ("Project Flow") for a solution and compare your work!
3. Continue to the "Project Flow" sheet for further instructions.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!