Question: Activity Description Immediate Predecessor Optimistic (weeks) Most Probable (weeks) Pessimistic (weeks) A Build Internal Component - 4 5 6 B Modify roof and floor -

Activity

Description

Immediate Predecessor

Optimistic

(weeks)

Most Probable

(weeks)

Pessimistic

(weeks)

A

Build Internal Component

-

4

5

6

B

Modify roof and floor

-

3

6

9

C

Construct collection stack

-

9

10

11

D

Pour concrete and install frame

A,B,C

12

13

14

E

Build high temperature burner

A

4

8

12

F

Install control system

D

4

5

6

G

Install air pollution device

D

1

4

7

Required:

  1. Calculate the expected time for each activity
  2. Construct the network diagram
  3. Calculate earliest start and finish times and latest start and finish times for the project.
  4. Determine the critical path for the project
  5. Determine the variance for the project
  6. Determine the probability that the project will be finished in (i) 12 days or less (ii) more than 12 days (iii) 20 days or more.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!