Question: Activity Description Immediate Predecessor Time (weeks) A Survey building site 5 B Develop initial design 7 C Obtain board approval A, B 10 D Select
| Activity | Description | Immediate Predecessor | Time (weeks) |
|---|---|---|---|
| A | Survey building site | 5 | |
| B | Develop initial design | 7 | |
| C | Obtain board approval | A, B | 10 |
| D | Select architect | C | 2 |
| E | Establish budget | C | 4 |
| F | Finalize design | D, E | 15 |
| G | Obtain financing | E | 13 |
| H | Hire contractor | F, G | 6 |
Develop the activity schedule for the project.
| Activity | Earliest Start | Latest Start | Earliest Finish | Latest Finish | Slack |
|---|---|---|---|---|---|
| A | |||||
| B | |||||
| C | |||||
| D | |||||
| E | |||||
| F | |||||
| G | |||||
| H |
(d)
Does it appear reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans? What is the expected completion time for the project?
Step by Step Solution
There are 3 Steps involved in it