Question: Activity Description Immediate processor Activity time ( weeks ) A Develop product - 5 B Plan marketing - 1 1 / 2 C Prepare manufacturing

Activity
Description
Immediate processor
Activity time
(weeks)
A
Develop product
-
5
B
Plan marketing
-
11/2
C
Prepare manufacturing
A
3
D
Build protype model
A
4
E
Prepare marketing
A
3
F
Prepare cost estimates
C
2
G
Run product
D
3
H
Complete market
B,E
31/2
I
Prepare pricing
H
2
J
Prepare final report
F,G,I
2
Activity
Optimistic time
Pessimistic time
Expected time
A
4
12
?
B
1
5
2
C
2
4
3
D
3
11
5
E
2
4
3
F
11/2
2/12
2
G
11/2
4/12
3
H
2/12
7/12
4
I
11/2
2/12
2
J
1
3
2
1)What is the entire time to complete the project?
2) What is the expected time for activity A?
3) What does pessimist time mean?
4) What the difference between optimist & pessimist time for respectively activities A and D tells you?
5) The Critical path is represented by activities A-E-H-I-J. What is the total
required time to complete the project?
6) What are the functionalities of the product?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!