Question: Activity Description Immediate processor Activity time ( weeks ) A Develop product - 5 B Plan marketing - 1 1 / 2 C Prepare manufacturing
Activity
Description
Immediate processor
Activity time
weeks
A
Develop product
B
Plan marketing
C
Prepare manufacturing
A
D
Build protype model
A
E
Prepare marketing
A
F
Prepare cost estimates
C
G
Run product
D
H
Complete market
BE
I
Prepare pricing
H
J
Prepare final report
FGI
Activity
Optimistic time
Pessimistic time
Expected time
A
B
C
D
E
F
G
H
I
J
What is the entire time to complete the project?
What is the expected time for activity A
What does pessimist time mean?
What the difference between optimist & pessimist time for respectively activities A and D tells you?
The Critical path is represented by activities AEHIJ What is the total
required time to complete the project?
What are the functionalities of the product?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock