Question: Activity Description Optimistic ( a ) Most Probable ( m ) Pessimistic ( b ) A Plan event 2 3 4 B Select location 2

Activity Description Optimistic
(
a
)
Most Probable
(
m
)
Pessimistic
(
b
)
A Plan event
2
3
4
B Select location
2
.
5
2
6
C Decide on speakers & vendors
4
4
4
D Prepare & mail brochures
2
4
6
E Update web site
1
.
5
2
.
5
3
.
5
F Final check with speakers & vendors
3
.
5
4
4
.
5
G Registration & hotel reservations
3
3
6
H Finalize last
-
minute details
2
5
5