Question: Activity Description Predecessor t e Variance: [(b-a)/6]2 A Planning None 5 4 B Analysis None 3 4 C Develop A 4 2 D Testing A
Activity Description Predecessor te Variance: [(b-a)/6]2
A Planning None 5 4
B Analysis None 3 4
C Develop A 4 2
D Testing A 2 2
E Licensing B 5 5
F Production C 2 3
G Promotion D 5 2
H Release E 2 1
I Closing F, G, H 3 1
What is the probability of completing the project in 17 periods?