Question: Activity Description Predecessors Duration A B C D E F G H I J K L M City Permit Bluestake Layout Excavation Plumbing Steel Electrical

Activity

Description

Predecessors

Duration

A B C D E F G H I

J

K

L

M

City Permit

Bluestake Layout Excavation Plumbing Steel Electrical Inspection Pouring Concrete

Finishing Concrete and Pool Tiles

Install Pool Equipment

Install Patio Tiles

Deliver to Customer

---

A A A, B,C D D,E F E,F,G H I

J

J

L

1

2 5 5 4 4 2 1 1 4

2

3

1

Calculate the CP for the project and estimate project duration (show your forward and backward calculations for the critical path)