Question: Activity Description Predecessors Duration A B C D E F G H I J K L M City Permit Bluestake Layout Excavation Plumbing Steel Electrical
| Activity | Description | Predecessors | Duration |
| A B C D E F G H I J K L M | City Permit Bluestake Layout Excavation Plumbing Steel Electrical Inspection Pouring Concrete Finishing Concrete and Pool Tiles Install Pool Equipment Install Patio Tiles Deliver to Customer | --- A A A, B,C D D,E F E,F,G H I J J L | 1 2 5 5 4 4 2 1 1 4 2 3 1 |
Calculate the CP for the project and estimate project duration (show your forward and backward calculations for the critical path)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!