Question: Activity Description Time ( hrs ) Immediate Predecessor ( s ) A Find location determine resource requirements 2 5 - B Requisition of lumber and

Activity Description Time (hrs) Immediate Predecessor(s)
A Find location determine resource requirements 25-
B Requisition of lumber and sand 65 A
C Dig and grade 95 A
D Saw lumber into appropriate sizes 35 B
E Position lumber in correct locations 20 D, C
F Nail lumber together 10 E
G Put sand in and under the equipment 25 F
H Put dirt around the equipment 15 F
I Put grass all over the garden, landscape, paint 30 G, H