Question: Activity Design Information Processor (DIP) Write Information Processor (WIP) Design Analysis Package (DAP) Write Analysis Package (WAP) Introduce System (INT) (a) (b) (c) (d)
Activity Design Information Processor (DIP) Write Information Processor (WIP) Design Analysis Package (DAP) Write Analysis Package (WAP) Introduce System (INT) (a) (b) (c) (d) Preceding activity DIP DAP WIP, WAP NORMAL Time Costs (Hrs) (Shs.) 32 40 50 24 120 640 480 1,000 288 4,800 CRASH Time Costs (Hrs) (Shs.) 20 30 30 15 70 Draw the network Identify the critical path What is the normal project duration and the associated cost? Crash the relevant activities systematically and determine the optimal project completion time 800 720 1,200 360 5,600
Step by Step Solution
3.52 Rating (162 Votes )
There are 3 Steps involved in it
Answer a Network Diagram INT 1000 DIP 640 WIP 20 DAP 32 WAP 40 CRASH 30 CRASH 24 CRASH 15 Proje... View full answer