Question: Activity Duration ( days ) Predecessor A 5 - - B 8 A C 7 A D 6 A E 9 B , C ,

Activity Duration (days) Predecessor
A 5--
B 8 A
C 7 A
D 6 A
E 9 B, C, D
F 10 B, C, D
G 5 E, F
On a piece of scratch paper, draw the network associated with this table and determine the following. What is the total slack for activity D?