Question: Activity Duration ( days ) Predecessor A 5 - - B 8 A C 7 A D 6 A E 9 B , C ,
Activity Duration days Predecessor
A
B A
C A
D A
E B C D
F B C D
G E F
On a piece of scratch paper, draw the network associated with this table and determine the following. What is the total slack for activity D