Question: Activity Duration (days) Predecessor A 5 -- B 5 A C 10 A D 4 A E 5 B, C, D On a piece of
Activity Duration (days) Predecessor A 5 -- B 5 A C 10 A D 4 A E 5 B, C, D On a piece of scratch paper, draw the early-start Gantt Chart associated with this table. Assume the project is resource-constrained but not time-constrained. Assume only one resource is available and that resource can only do one activity at a time. Given that the Month of May has 31 days, what would be the completion date for the project