Question: Activity Duration Immediate follower A 1 B , C , D , E B 3 F C 4 F D 2 F E 4 F

Activity
Duration
Immediate follower
A
1
B, C, D, E
B
3
F
C
4
F
D
2
F
E
4
F
F
4
G
G
1
-
From the AoN in question 1(above), identify the critical path(s).
1.
A, B, F, G
2.
A, C, F, G
3.
A, D, F, G
4.
A, E, F, G
5.
A, C, F G and A, E, F, G

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!