Question: Activity Duration in weeks Immediate Predecessor ( s ) Max Weeks Can Be Crashed Crash Cost: $ per week A 4 - 2 $ 8

Activity Duration in weeks Immediate Predecessor(s) Max Weeks Can Be Crashed Crash Cost: $ per week
A 4-2 $84,000
B 6 A 3 $22,000
C 7 A 3 $33,000
D 4 A 2 $21,000
E 8 B, C 2 $42,000
F 4 C, D 2 $22,000
G 4 E, F 1 $82,000
Due to recent labor strikes, Netflix has fallen behind schedule. Netflix would like to reduce the length of the project by 2 weeks at minimum cost.
Draw an Activity-on-Node Network to represent this project.
Find the critical path.
Determine the most cost-effective way to reduce the length of the project by 2 weeks.
Enter the total incremental cost of crashing the project by 2 weeks for your minimum cost plan.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!