Question: Activity Duration (week) Predecessors C,ED a) Draw AOA network diagram (grading will be done only for AOA, not AON) (12 pts) a) When will the

Activity Duration (week) Predecessors C,ED a)
Activity Duration (week) Predecessors C,ED a) Draw AOA network diagram (grading will be done only for AOA, not AON) (12 pts) a) When will the project be available (completion of project)? (2 pts) b) What is the effect on the project if activity E takes an extra week? (3 pts)