Question: Activity Duration (weeks) crash time (weeks) Description preceding activity(ies) crashing cost/week A 7 Determine gala theme B 5 Reserve portal location for gala A C

Activity Duration (weeks) crash time (weeks) Description preceding activity(ies) crashing cost/week
A 7 Determine gala theme
B 5 Reserve portal location for gala A
C 7 6 Create marketing plan B $1,500
D 6 3 Ray Parker Jr. to audition musical acts B $1,100
E 6 4 determine ticket sales method C $1,000
F 7 4 purchase supplies, including Stay Puff marshmallows C $750
G 4 3 pick musical act and sign contract D $250
H 4 2 sell tickets in person E $500
I 5 4 sell tickets online E $1,250
J 1 Gala H,I,F,G

How much will it cost to reduce the original total project time by four weeks?

How much did crashing last (fourth) week cost?

If Egon had a budget of only $2,000 for crashing costs, what is the shortest possible completion time?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!