Question: Activity Duration (weeks) Dependency Resources A 8 4 B 2 A 2 C 3 A 3 D 10 A 2 E 12 B 4

Activity Duration (weeks) Dependency Resources A 8 4 B 2 A 2 C 3 A 3 D 10 A 2 E 12 B 4 F 8 B 3 G H I J 25 96 C E E,F,G 6 H 4544 K 5 I,J 3 L 4 D,G,K 5 a) Draw a project network from the table above b) What activity(s) is a burst activity? ii. What activity(s) is a merge activity? iii. What is the length of the project? iv. What is the critical path? c) Draw the Gantt chart d) Assuming there are only 10 resources available for the duration of this project, how can the schedule be best adjusted to level the resources? e) Revise the Gantt chart to reflect this resource availability.