Question: Activity Duration ( weeks ) Immediate Predecessor ( s ) A 5 - B 6 A C 5 A D 1 0 A E 8

Activity Duration (weeks) Immediate Predecessor(s)
A 5-
B 6 A
C 5 A
D 10 A
E 8 A
F 12 B,C
G 11 D,E