Question: ACTIVITY DURATION (WEEKS) PRECEDES A (start) B, C B E c F E 2. F(end) 2 Assume that the activities have the following costs to

ACTIVITY DURATION (WEEKS) PRECEDES A (start) B, C
ACTIVITY DURATION (WEEKS) PRECEDES A (start) B, C B E c F E 2. F(end) 2 Assume that the activities have the following costs to shorten: A $300/week: B. $100/week: C S200/week: E S100/week, and F. $400/week. Assume also that you can crash an activity down to 0 weeks in duration and that every week you can shorten the project is worth $250 to you. What activities would you crash? What is the total crashing cost