Question: Activity Duration ( weeks ) Predecessors ES EF A 2 . 5 None 0 enter your response here B 1 None 0 enter your response

Activity
Duration(weeks)
Predecessors
ES
EF
A
2.5
None
0
enter your response here
B
1
None
0
enter your response here
C
7
A, B
enter your response here
enter your response here
D
6.5
A
enter your response here
enter your response here
E
6.5
C
enter your response here
enter your response here
F
7.5
D, E
enter your response here
enter your response here
G
0.5
F
enter your response here
enter your response here
H
2.5
E