Question: Activity durations are determined by: Question 5 options: Project team estimates The client The project sponsor Budget projections Which statement about the project critical path
Activity durations are determined by:
Question 5 options:
|
| Project team estimates |
|
| The client |
|
| The project sponsor |
|
| Budget projections |
Which statement about the project critical path is not true?
Question 2 options:
|
| There can only be one critical path in a project |
|
| There can be more than one project critical path |
|
| If two paths in the project are equal, and they are both the longest project path, then they are both the critical path. |
|
| It should not be inferred that activities outside the critical path are unimportant |
The purpose of the Gantt chart is
Question 4 options:
|
| To communicate activity durations and milestones |
|
| To perform critical path analysis |
|
| To analyze the logical order of events |
|
| To conduct the forward and back pass |
When three activities are scheduled in parallel, the critical path activity will be found on:
Question 8 options:
|
| The shortest duration activity |
|
| The longest duration activity |
|
| The activity that is most important to the project |
|
| The activity that uses the most resources |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts