Question: Activity Duration(Weeks) Predecessors Possible Crashing(Week) Crashing Cost per Week A 5 None B 7 A 1 $400 C 3 B 1 $300 D 7 B

Activity Duration(Weeks) Predecessors Possible Crashing(Week) Crashing Cost per Week
A 5 None
B 7 A 1 $400
C 3 B 1 $300
D 7 B 2 $500
E 3 C,D 1 $700
F 2 E

EF, ES, LS, LF help.